Manila BIT Data Center, Philippines

approx. 3,200 tons

Total Tonnage

Manila BIT Data Center, Philippines

Completion

2023

Location

Manila, Philippines

Category

Overseas Projects

Have a steel fabrication or procurement need?

Send your drawings and quantities for a drawing-based review and quote.

FindingSteel (GUANGDONG JIANGXIN AUTO-MANUFACTURE STEELSTRUCTURE CO., LTD., Foshan Gaoming) fabricated and supported installation of BIT Data Center steel in Manila. Case file: about 28,000 m² GFA, about 3,200 tons. Fire protection and coating follow approved drawings. Not the civil main contract.

Construction Process

Detail Design
Scheduling
Fabrication
Quality Inspection
Installation
01

At a glance

• BIT Data Center, Manila • GFA about 28,000 m² • Steel about 3,200 tons • Scope: fabrication and installation support
02

Project overview

The BIT Data Center in Manila, Philippines is an important digital infrastructure project in Southeast Asia, with a total floor area of approximately 28,000 square meters and a steel structure weight of around 3,200 tons.
03

Technical highlights

• Data center special structural design: Using high-bearing-capacity steel frame structure to meet special requirements for data center floor loads. • Fire and corrosion double protection: Steel structure surface uses thick fire-resistant coatings with 2-hour fire resistance. • BIM fine modeling: Using Tekla Structures for high-precision 3D modeling. • Precise floor height control: Through deepening design to optimize beam height, ensuring computer room clear height of not less than 3.2m. • Seismic reinforcement design: Designing according to Philippine National Building Code (NBCP).
04

What we supplied

• Data center steel structure deepening design: Special deepening design based on server cabinet and precision equipment parameters. • High-precision steel component fabrication: Using CNC equipment to fabricate various connection components. • Shipping and customs clearance services: Providing full logistics services from domestic factories to Manila Port. • On-site installation and debugging: Dispatching installation teams to provide on-site guidance.
05

Quality and delivery

• Detailed to the hall grid; re-measured to the drawing before packing. • Fire and coating to the specification; the 800 kg/m² live load is not stated here.
06

Key figures (case-file, approx.)

Location: Manila, Philippines GFA: about 28,000 m² Steel: about 3,200 tons Plant: Yanghe, Gaoming, Foshan; 25,000 m²; 40,000 t/year
07

FAQ

Q1: Can 800 kg/m² live load be published? A: No. Unconfirmed in the register; omitted. Q2: Did Jiangxin take the MEP main contract? A: No. Scope is the steel frame. Q3: What is needed for a quote? A: Drawings, quantities, span/loads, coating or fire-protection requirements.

Have a steel fabrication or procurement need?

Send your drawings and quantities for a drawing-based review and quote.